PERI GmbH, Construction Exercise 2010|2011, Short Description

Task description 2010|2011 - Short description

1.Building site equipment
1.1Determine all necessary specific values.
1.2Choose all necessary equipment items.
1.3Draw a plan of the construction site setup.
  
2.Bid documents for concrete and reinforcement work
2.1Create a list with all positions titled concrete and reinforced concrete with hourly estimates and material costs with reference statements.
2.2Create a bid for the concrete and the reinforced concrete work.
  
3.Choice of procedure / calculation
3.1Comparison of slab formwork systems: MULTIFLEX  - SKYDECK
3.2Comparison of wall formwork systems: TRIO 270  - MAXIMO 270
  
4.Formwork solutions
4.1Create all necessary formwork solutions for the straight walls with the PERI MAXIMO 270.
4.2Create all necessary formwork solutions for the slabs with PERI SKYDECK.
4.3Create a formwork solution for the round wall found in the basement with PERI RUNDFLEX.
  
5.Details of construction implementation
5.1Create a barrier free solution to overcome the height difference between the street and the building entrance on the east side of the building.
5.2Plan a ground superstructure for the parking area and bottom slab. Make a sketch of these respectively.
5.3Describe the necessary actions needed to install the cisterns.
  
6.Construction development plan
6.1Create a rough draft.
6.2Create a detailed plan for the basement of the office building.