4.20 m high VARIO GT 24 was used for the core and retaining walls, single sided in combination with SB-B brace frames. 21 sets LICO column formwork helped to pour 60 cm x 60 cm up to 130 cm x 130 cm columns.
At the Al Muneera project in Abu Dhabi, Al Futtaim Carillion chose to use the VARIO GT 24 system for walls and columns as it could be used in all areas, being a versatile system with a built in safety.
The Ulm University is being enlarged by a new clinical centre at the moment. PERI ensures the quick construction progress with a comprehensive formwork solution.
For the construction of the new balneotherapy centre, different circular structures could be realised accurate to dimension with the help of the further developed RUNDFLEX Plus.