Housing

PERI GmbH - Safari Drive Condominiums, Scottsdale, Arizona PERI GmbH - Safari Drive Condominiums, Scottsdale, Arizona

Safari Drive Condominiums, Scottsdale, Arizona




Deep Beams formed
with SKYDECK and TRIO


Vanguard Properties is currently developing a 215 unit modern neighborhood on a 4.9 acre waterfront in upscale Scottsdale. Concrete Structures worked with PERI to shore a large 70,000 ft² (6,500 m²) main level deck that will later support the steel structure of the numerous overlying residential and commercial buildings.

Construction joints required shoring layouts in excess of 16,000 ft² (1,485 m²) and the first pour alone required over 750 yd³ (573 m³) of concrete. The graded beams were 53" (1.30 m) deep and 2 ft (61 cm) wide and were poured concurrently with the 12" (30 cm) deck.

PERI Systems In Use
  • TRIO
  • SKYDECK Aluminium Panel Slab Formwork

  • Clinton Stubbs


    Project Superintendent

    “The PERI formwork solution kept this first level deck pour very simple. The SKYDECK can be used any- where on site and the engineering support we received allowed us to efficiently cycle this equipment between two neighbouring jobsites.”

    Contractor: Concrete Structures Inc., Phoenix
    Field Service: PERI Phoenix
    Field Service: PERI Formwork Systems, Inc., USA
    PERI scope 02/2006, USA, Canada
     
    Google +
    LinkedIn
    Twitter