Multi-Storey Buildings

PERI GmbH - Tech Lab, Munich Solln, Germany PERI GmbH - Tech Lab, Munich Solln, Germany PERI GmbH - Tech Lab, Munich Solln, Germany

Tech Lab, Munich Solln, Germany




FTF Facade formwork:
Safe and efficient assembly of perfabricated facade panels


For the construction of this 35,000 m² laboratory and office building, the façade panels and beams were integrated as pre-fabricated sections in the in-situ concreted columns and slabs using the FTF facade formwork. This ensured that the pre-fabricated sections were securely assembled, aligned and concreted with the columns and slabs.

Apart from a very high degree of safety – an integrated working platform protects the site personnel from any risk of falling. There is the possibility to position the prefabricated sections simply and precisely. Additional erection of scaffolding is not necessary.

Source: PERI scope, 1/2003

Contractor: Wolff & Müller, Stuttgart
Project supervision: PERI Stuttgart
Field Service: PERI GmbH, Deutschland