For the construction of the two 21-metre high reinforced concrete cores, the contractor consortium of Schick with Völkel & Heidingsfelder, opted for cost-effective PERI formwork combinations.
With the SKYDECK panel slab formwork, concreting cycles totalling over 2,000 m² could be efficiently shuttered. The SKYDECK drophead system allowed early striking to take place and resulted in reducing on-site requirements of main beams and panels.
For realizing the concrete frame as well as the finishing work, construction progress could be accelerated through the use of PERI system equipment. The straight and circular wall sections could be cost-effectively constructed with TRIO and ...
The Adolfo Ibáñez Foundation provided the funding for a new university building with auditoriums, lecture halls and a large atrium on the inside, and was completed in a period of only 16 months.
For the different wall heights, ranging between 4.70 m and 10.50 m, fast shuttering times could be achieved with the TRIO panel formwork. PERI UP reinforcement scaffold was available for forming, reinforcement and concreting work required for ...