Palm paper mill, United Kingdom
Project data
Location: King's Lynn, United Kingdom
Europe’s largest and most modern paper mill, 600 m long, 100 m wide and 30 m high
Construction period until opening: 2008 - 2009
Requirements
- tight schedule
- coordination of shell construction and machine assembly
- shear walls with a thickness of 1.50 m to 2.00 m
Customer
Glass GmbH, Mindelheim, Germany
Customer's benefit
- construction time finished three weeks before schedule
- fast shuttering times
Stefan Bucher
Construction Manager
In my opinion, PERI UP is two thirds faster than common scaffolding systems. On the one hand, we are able to erect it fast and safely, and on the other hand, we achieve an efficient construction sequence due to the flexibility and versatility.
PERI solution
- optimally harmonised formwork and scaffolding solution
- outside work scaffold for safe shuttering, reinforcement and pouring of the 9.90 m high walls
- shoring for protruding site-mixed concrete slabs and as temporary support of the FT beams
- scaffolding staircase access to the work places